“Modular construction has become the construction method of choice for the quality-and cost-conscious house buyer. The best-built modular homes are better built than the vast majority of stick-built homes. Modular homes offer better materials, state-of-the-art construction technology, superior finished quality, and time and money savings. And you gain all of these benefits without sacrificing design or amenities.”
THE CONSTRUCTION MANAGER'S
RESPONSIBILITIES FOR A MODULAR HOME
Your CM needs to complete three types of construction tasks to build your modular home: the site work, the "button-up" work, and the construction of site-built
structures.
The site work includes everything done to the land so you can build a home on it. Some of this work is done before the home is delivered, and some of it is done after. The site work
includes:
- Clear the land of trees
and misc.
- Dig for foundation hole
- Install a driveway
- Install a foundation 8' 9'
to 12'
- Grading for proper
drainage
- Install a septic system or
hookup to municipal sewer and water per municipality
Button-up work includes finishing a modular home after it is set on the foundation. This
includes:
- Connect the plumbing and
electrical systems
- Install the HVAC system
- Complete the exterior
carpentry
- Complete the interior
carpentry
Site-built structures are additions to a modular home, as
follows:
- Garage
- Porch
- Deck
- Masonry fireplace
- Wet room
- Finished basement

Typical CM site and
foundation work. Some of these tasks will be done before
the home is delivered; others will be done after.
Each set of tasks requires a different base of knowledge and a different set of construction skills. Together, these tasks require the services of experienced contractors in several different construction trades. For example, you will need an excavator, foundation contractor, plumber, electrician, HVAC (heating, ventilation, and air conditioning) contractor, siding contractor, carpenter, floor installer, drywall finisher, and painter. If you also build a garage, you will need a roofer. Sometimes the same contractor will have more than one skill, so the person who frames your garage might also shingle it. As general rule, however, you will need several different people to complete the work, and most of these will be independent contractors, working for themselves or a small company. Consequently, you will need someone to coordinate the work of these contractors and to oversee and manage the project from start to finish. That individual is the construction manager (CM).
HOW TO CHOOSE A CONSTRUCTION
MANAGER
A professional CM with modular home experience will be the best-equipped person to handle all of these jobs. Whether you decide to act as your own CM or hire a professional, the knowledge you acquire on site will help you have a more successful experience building your modular home.

BEFORE SET
DAY
Before beginning any work on your property, the CM should complete several other
tasks.
-
What is a site
plan and why should the CM complete one?
-
What is an
as-built plan and who might require one?
-
Why a basement
layout plan is important to you and what information should
the CM include?
-
When do you need
the CM to complete an attic layout plan?
-
Which
construction plans should the CM complete before beginning
construction on your site built structures?
-
Which
construction specifications must the CM supply to the dealer
before the manufacturer can begin building your home?
-
What are your
responsibilities for keeping the CM up to date about the
changes you and the dealer make to your home?
-
What nineteen
permit related issues might you and your CM need to deal with
before you can get a building permit?
-
Are you or the
CM responsible for paying for the building permit and any
related fees?
-
When should the
electrical company be contacted and who should do this?
-
What is a
preconstruction meeting and why should the CM conduct one with
you?
COMPLETING
THE SITE WORK
The CM must complete all of the site
work.
-
Before the CM
begins excavation, who should he contact to determine if your
property contains underground utilities (gas, electric, water,
sewer, phone or cable)?
-
What steps
should the CM take to protect against frost and snow, if you
are building during the winter months in colder regions?
-
If you are
building during the spring, why should the CM find out if your
community allows heavy equipment to travel on the roads during
the spring?
-
If the CM needs
to demolish any existing structures on your property, how
should he dispose of the materials?
-
When should you
purchase a propane gas tank, and if you do so, should you have
it buried on your property?
-
Should you
install radon protection under the basement floor?
-
Who will do the
landscaping on your property and which tasks will need to be
done to prepare the property?
PREPARING THE
SITE FOR DELIVERY AND SET
The CM is responsible for preparing the site for the delivery and set of the modules. More specifically, he is responsible for preparing both the access leading to the lot and foundation, and the area where the crane and modules must be located during the set. If the area is flat, with good soil conditions and relatively wide, straight roads, this responsibility may be without challenges. On the other hand, problems can arise on what appears to be an easy site. Bad weather, poor soil, loose fill, a utility pole in an inconvenient place, a septic system located where the crane needs to go, a customer's refusal to cut a favored tree or remove an old stone wall; these are the kinds of things that can turn a site into a logistical challenge, or even a logistical nightmare.
When the manufacturer's delivery time from its factory to the site is more than a couple of hours, it will deliver the modules at least one day before the scheduled set. In such a situation, the CM should try to create sufficient space on the site to store all of the carriers overnight. Since the most efficient way to set a home on the foundation is to place the crane in front of the foundation with one carrier on each side of the crane, the preferred storage plan is to create a space wide enough for the carriers to be delivered directly to these positions. Unfortunately, the combination of lot size and configuration, topography, soil conditions, foundation size, and the number and size of the modules can sometimes make it impossible to place all of the modules in the right place while preserving room for the crane to set up.
When the modules cannot be properly placed, one or more of the carriers have to be delivered to a temporary storage location, which may be at another location on your site or at a nearby parking lot or open field. The carriers will then be moved to their proper positions next to the foundation on set day. Although the CM is responsible for preparing the site to facilitate these efforts, he is not responsible for things beyond his control, such as a heavy rainstorm that washes out the driveway. Nor should you expect him to pay for the required repair.
If the CM does not prepare the site in a satisfactory manner, and this causes the delivery and set operations to be delayed, you and the CM will be liable for the additional costs incurred. The drivers and escorts that deliver the carriers will budget enough time to
directly to the site or wherever you designate. They will expect to maneuver the carriers into place with reasonable effort, and then leave. They will not expect to spend hours waiting for trees to be cut, fill to be delivered, or a bulldozer to arrive. If any of these are required, the delivery company will charge the modular dealer, who will in turn bill you, for the additional time. The crane company will charge the dealer by the hour, with a minimum fee. The longer the set takes, the more the meter runs. The crew that completes the various set activities will also charge the dealer for any lost time caused by the delays, and the dealer will pass this additional expense on to you. If the delays were caused by the CM's poor site preparation, it fair for you to submit the invoices from the delivery, crane, and set companies to the CM for reimbursement.
Many sets take a full day, and some take two or more days. One of the most important responsibilities of the set crew is to protect the home from weather damage as quickly as possible. If the site is not prepared, and the set is subsequently delayed by several hours, the set crew may not be able to complete enough of the set to give your home the protection it will need should it rain over night. If the delay happens before the first module is set, the set crew and modular dealer can cancel the set and reschedule it for the next available day. But if some of the modules are already set on the foundation, with the protective coverings removed, the set cannot easily be stopped and the crew may not be able to take the required steps to protect the home until the cause of the delay is removed. If this delay takes a few hours, the home will be exposed to the elements longer than it needed to be.
| The crane and modules can be positioned in several ways. The top three positions are preferred when the topography of the land and size of the modules allow them. The modular dealer will advise the CM about which situation will work best for your site. |

With these issues in mind the CM answers the following
questions:
-
What is the best
way for your dealer and the CM to avoid a disagreement about
what needs to be done to prepare your site properly?
-
When are
overhead objects likely to become obstructions?
-
How should the
turns along the driveway be prepared so that they can be
negotiated by the transporters (tractor-trailers) that will
deliver the modules?
-
What do you do
if the modular transporters and carriers can only enter your
property by driving across a part of a neighbor's property?
-
How wide the
driveway should be made?
-
Where should the
CM create a compacted and level gravel base?
-
What are
considered ground level obstructions?
-
What should the
CM do if needs to install underground pipes or tanks?
-
When must the CM
delay completing the excavation and foundation work for
on-site structures?
-
Who is
responsible for keeping your site free of snow and ice?
-
What should be
done if it snows inside your foundation before the house set?
-
How big of an
area should be prepared for the crane and how is this done
properly?
-
What needs to be
done if the CM cannot provide sufficient room on site to store
the modules overnight?
-
When should the
CM provide heavy equipment to assist the delivery crew and
what might this equipment be used to do?
-
What equipment
might be need on set day to assist with placing the modules
within reach of the crane?
-
Where should the
carriers be stored after the set?
INSTALLING THE
FOUNDATION
In many ways, installing the foundation for a modular home is the same as for any other home, and there is no need to elaborate on the requirements here. The CM and his foundation subcontractors should know what to do. However, the following issues are unique to modular
homes:
-
Can a modular
home be installed on a crawl space? How about on a slab?
-
What are the
potential consequences if the CM does not have the foundation
ready when the house is scheduled to be delivered?
-
Who determines
if the foundation is ready to bear the weight of a modular
home?
-
How closely must
the foundation for a modular home follow the manufacturer's
dimensions?
-
What type of
plan is the manufacturer likely to provide for the foundation,
what additional information must be added to the plan, and who
will add the information?
-
When can the CM
change the location of the support columns?
-
What are the
options for replacing support columns with beams?
-
Must the CM
create an entry to your basement or crawl space, and what are
the advantages of exterior vs. interior entries?
-
Should the CM
install a poured-concrete or block foundation wall, are piers
and pilings viable options, and should you consider a precast
foundation system?
-
What should the
CM do if the building codes and manufacturer's specifications
differ for installing the foundation?
-
What seven
details should the CM keep in mind when planning your
foundation?
-
What are the
relative advantages of pouring the foundation floor before or
after the house is set on the foundation?
-
Should the CM
backfill around the foundation before or after the house is
set?
-
Should the CM
install a single or double sill plate?
-
What is the
significance of an unlevel foundation for a modular home and
what can be done to correct for this?
-
What special
steps must the CM take if your foundation has knee walls and
walk-out walls?
-
What types of
support columns are best, how tall should they be, and what
type of top plates should be used?
-
Does the CM or
set crew install support beams and flitch plates?
-
What should your
CM do if snow or ice accumulates in your foundation before set
day?
DELIVERY DAY AND
SET DAY RESPONSIBILITIES
The CM's responsibilities for delivery and set day
are:
-
How the CM can
help the set delivery and set crews
-
The steps the CM
can take to ensure everyone's safety
-
The CM's
responsibility for providing a construction site toilet
-
What the CM
needs to do about the large amount of trash generated by a set
-
Then the CM
might have to complete some tasks involving the home's roof
-
When the CM has
special obligations for protecting the modules from the
weather immediately after the set
-
How much
additional work the CM needs to complete when you order
panelized structures from the dealer
-
The CM's
responsibility for handling the "ship loose"
inventory
-
What the CM
should do to secure your home from unwanted entry while
keeping it accessible to the contractors who will complete the
work
BUTTON-UP
RESPONSIBILITIES
Once the set is complete, the CM can complete the button-up work on your modular home. He will need to finish the interior and exterior carpentry and hookup the plumbing, heating, and electrical systems. The following tasks are described in detail in this
chapter:
-
Protecting the
interior surfaces - such as finished flooring, countertops,
and bathtubs - during the button-up
-
Air sealing the
modules to make the home energy efficient
-
Preparing the
exterior of the house for siding installation
-
Installing the
side, soffit, fascia, and decorative exterior fixtures, such
as shutters, door pediments, window mantles, trim boards, and
dentil moldings
-
Completing
interior and exterior basement access stairs
-
Removing
foundation ties
-
Sealing water
and sewer pipe penetrations in concrete walls
-
Providing
temporary heat during the cold months
-
Using the
as-built mechanical plans
-
Completing the
electrician's responsibilities
-
Completing the
plumber's responsibilities
-
Completing the
HVAC contractor's responsibilities
-
Installing the
water heater
-
Securing copies
of the equipment manufacturer's product literature and
warranty information
-
Constructing the
chimney chase for zero-clearance fireplaces
-
Installing a
masonry fireplace

The CM must ensure that the home is sealed against air infiltration
where two modules are joined, both side to side and top to bottom,
as well as where the modules sit on the foundation.
-
Completing the
interior button-up, including preparation of all marriage wall
openings, installation of marriage wall doors, moldings, and
drywall, and adjustment techniques
-
Locating and
using the ceiling and floor access panels
-
Insulating the
attic access
-
Installing
special ship loose items that are normally installed
-
Installing the
vents for bathroom ventilation fans, clothes dryers, and range
hoods
-
Building a shaft
for a skylight
-
Constructing a
tray ceiling
-
Completing a
cathedral ceiling with or without a loft
-
Completing the
entry of a raised ranch or split level design
-
Installing the
stairs and railings to the second floor of a two-story or the
attic of an unfinished Cape Cod
-
Building a
"close-off" in the attic of an unfinished Cape Cod

How to join two modules at a marriage-wall opening.
-
Completing the
special tasks required for a three-module Cape Cod
-
Insulating the
basement, and band boards
-
Installing the
finished flooring
-
Painting and
staining
-
Constructing
exterior entrances at all doors
-
Installing
miscellaneous materials, such as window grills and screens,
gutters, and storm doors
-
Building
additional structures on site, such as garages, porches,
decks, sunrooms, finished basements, and the second story of
unfinished Cape Cods
[return
to the top]